Arizona could become home to one of the nation’s largest artificial intelligence and supercomputing facilities as Elon Musk’s SpaceX pursues a massive $50 billion development in Cochise County that could create thousands of jobs and generate millions in new tax revenue.

The ambitious proposal calls for a 747-acre supercomputing and artificial intelligence data center campus near the unincorporated community of Cochise, approximately 60 miles southeast of Tucson. Located near Willcox Playa and about 10 miles southwest of Willcox, the development would represent one of the largest technology investments ever proposed in Arizona.

SpaceX, through applicant Tombstone Resources LLC, is seeking a special use permit from Cochise County to develop the campus. Construction could begin as early as 2027, pending regulatory approvals and agreements to secure the project’s enormous electricity requirements.


MORE NEWS: Nominations are now open for the 2027 RED Awards

DEEPER DIVE: Overflow crowd celebrates winners of the 2026 RED Awards


Thousands of jobs and major economic impact

If completed, the project could deliver a significant economic boost to southeastern Arizona.

According to SpaceX, construction employment could peak at approximately 5,500 jobs, while the completed facility would support an estimated 1,000 permanent positions.

Those jobs would range from engineering, construction and skilled trades during development to computer hardware operations, networking, facilities maintenance, security and logistics once the campus becomes operational.

The company also projects substantial tax benefits for the region, including between $34 million and $103 million in additional annual property tax revenue and a potential $250 million in one-time county sales tax revenue.

SpaceX says its investment would support local infrastructure, public education and essential community services, although specific benefits would depend on final agreements and the project’s ultimate development.

A massive campus built in four phases

The proposed development would be constructed in four phases and could eventually include nine computing buildings, each measuring approximately 493,000 square feet.

At full buildout, the buildings alone would total approximately 4.4 million square feet, making the campus a potentially transformative addition to Arizona’s growing technology and data center industry.

The facility would be designed to train SpaceX’s advanced artificial intelligence models and support applications in scientific research, engineering, manufacturing, medical research, emergency response and national security.

However, the scale of the development presents a significant challenge: electricity.

The campus could require approximately six gigawatts of power at full buildout, along with a proposed 24-gigawatt-hour battery energy storage system.

SpaceX plans to invest approximately $3.6 billion in transmission and substation improvements, with additional energy investments potentially incorporating solar power and other renewable sources.

Electricity agreements remain a critical hurdle

The proposed site is located next to Arizona Electric Power Cooperative’s Apache Generating Station.

Arizona Electric Power Cooperative (AEPCO) would serve as the wholesale power and transmission provider, delivering electricity through Sulphur Springs Valley Electric Cooperative (SSVEC).

However, the electricity arrangements are not yet finalized.

According to SSVEC’s published project information, no Energy Services Agreement has been completed. The developer and utilities must negotiate terms, conduct engineering studies and secure necessary infrastructure before the project can move forward.

A final agreement would also require approval from the Arizona Corporation Commission.

Although currently identified network improvements could support the project’s initial phase, subsequent phases would require additional studies, investments and system upgrades.

AEPCO’s framework also calls for large electricity customers to fund necessary improvements and provide financial protections intended to prevent existing cooperative members from absorbing project-related costs.

Water conservation central to the proposal

With water availability a continuing concern across Arizona, SpaceX is emphasizing a cooling system designed to minimize water consumption.

According to the application, the campus would use closed-loop liquid cooling and dry coolers rather than traditional evaporative cooling towers.

The company estimates the completed facility would consume approximately seven to 10 acre-feet of water annually, primarily for domestic use by employees.

That amount is roughly equivalent to the annual water consumption of 20 to 30 Arizona households, according to the application.

The project would not require a new groundwater production well. Nonpotable water needs would be met through treated wastewater from the neighboring Apache Generating Station or water transported to the property.

Those figures remain applicant estimates and have not been independently verified by Cochise County.

Arizona’s technology ambitions expand

The proposed campus would add another major development to Arizona’s expanding technology economy, which has attracted significant investment in semiconductor manufacturing, advanced manufacturing, artificial intelligence and data infrastructure.

For Cochise County, the potential economic implications are particularly significant.

A project of this magnitude could generate construction activity, attract skilled workers, expand the local tax base and create opportunities for businesses throughout southeastern Arizona.

However, the proposal remains in its early stages, and the economic projections depend on obtaining approvals, securing electricity and completing the planned development.

The Cochise County Planning and Zoning Commission is scheduled to consider the special use permit application during a public meeting on Dec. 9, 2026.

County officials emphasize that the project has not been approved and that the applicant’s infrastructure, employment and operating estimates have not been independently verified.

If the development moves forward, SpaceX’s proposed $50 billion investment could position southeastern Arizona as a major center for next-generation artificial intelligence computing while bringing unprecedented economic activity to Cochise County.