May 15, 2015
Sky Harbor conducts 440KSF flooring project
Phoenix Sky Harbor Terminal 4 Terrazzo Project
Developer: City of Phoenix
General Contractor: McCarthy Building Companies
Architect: Richard-Bauer
Location: 3400 E. Sky Harbor Blvd., Phoenix
Size: 440KSF
Value: $15.4 M
Start/Completion: Contract State Date 9/1/2015 – Contract Complete Date 10/2019
Project Description:
Phoenix Sky Harbor International Airport is replacing approximately 440,000 square feet of flooring in the high traffic areas of Terminal 4 (T4) with terrazzo flooring. The main terminal areas include the high-traffic areas of concourses N1, N2, N3, N4, S3 and S4.
The project is within an operational airport and the construction will be phased over multiple fiscal years to maintain all operating functions.